您的当前位置:首页正文

索赔报告格式

2024-07-21 来源:尚车旅游网


LETTER HEADING

TO: COP

Attn.: CC.:

Dear Sir,

Ref.: 98/CPB/101 DATE: Nov. 12,1998

SUBJECT: BRIDGE COLLAPSE DUE TO FLOODING

With reference our letters Ref.: 97/CPB/104 dated ______ and Ref.: 97/CPB/105 dated _____ and in accordance with Conditions of Contract, Clause 2..39.3-FORCE MAJEURE, we now submit our request for:

(a) an extension of time, which is

TWELVE (12) days. This 12-day period for extension of Contract time is the period by which the pipeline (677-840km) construction activity by SPREAD NO. 10 was delayed due to lack of pipes resulting from the bridge collapse at El Gadambalia. This activity, with its early finish date being July 20, 1999, is a critical activity which governs the completion time of the whole of Segment A.

For details, please refer to Attachment l- DELALY STATISTICS BETWEEN 1-13 SEPTEMBER

Attachment 2- MONTHLY PROGRESS REPORT (M/R-August 30& September 30, 1998). Attachment 3- ORIGINAL SCHEDULE VS UPDATED SCHEDULE: CPM ANALYSIS

(b) an amount of cost compensation, which is

FIFTEEN THOUSAND ONE HUNDRED AND TWENTY TWO US DOLLARS ( US $ 15120 ) For details, please refer to Attachment4- COST CALCULATIONS.

We expect your acceptance and confirmation of the above request.

Thank you.

Yours truly,

CHINA PIPELINE

(Signature)

Project Manager

因篇幅问题不能全部显示,请点此查看更多更全内容